SPLOST VII Completed Projects

Police Department: 

  • IT Remodel – completed – the department completed an IT Unit with a room for servers to include the in-car camera servers, body-camera servers, and interview room servers. The new area also includes offices for IT personnel.

  • Investigations Remodel – completed – outdated cubicles (over 20 years old) were replaced with walls and doors for each detective, wired with electricity, lighting, and IT cables, allowing for privacy and also making more room for additional detectives.

  • In-Car Camera System – completed – in 2014 the department added an in-car camera system for the patrol bureau which includes a dash camera, rear seat camera, and wireless download of all videos at police headquarters.

  • Radio System Upgrade – between the city and county, a 6.5 million dollar upgrade of the city/county radio system was completed. The new system moved the radio system to an all-digital system, added new radio equipment and antennas at the 911 Center and at different radio antenna stations throughout the city/county, and doubled radio capacity. The upgrade is good for 20 years.

  • New Handheld radios – completed - between the police and fire departments, all old analog radios were replaced with new handheld digital radios (walkie-talkies) to match the new city/county infrastructure. The previous radios were over 15 years old.

  • SWAT Team Equipment – completed – all out-of-date SWAT Team to include but not limited to helmets, shields, gas masks, etc. were updated because this equipment has expiration dates.

  • Mobile Command Vehicle – the consoles on the command truck was updated from analog consoles to new computerized/digital consoles. There are three consoles (police, fire, and EMS). The consoles tie in different radio systems (800 MHz, VHF, and UHF) to allow for inoperability communications.

Engineering: 

Road resurfacing, drainage improvements, intersection improvements, street maintenance repairs, piping of ditches, traffic improvements, and sidewalk improvements throughout the city.

 

South Troup Street Project: 

A large group of citizens and community leaders gathered in December of 2016 for the ribbon cutting of the S. Troup Street Enhancement Project. The completed project runs from Griffin Avenue to Martin Luther King Jr. Drive in one of Valdosta’s oldest neighborhoods. Funded by SPLOST VII, the project positively impacts the quality of life within the neighborhood through the construction of new sidewalks on the east side of the street, crosswalks, new street signage, curb and gutter, bicycle lanes, underground storm sewer and drainage inlets, new driveway aprons, and new water & sewer service connections.

 

Public Works:

The Public Work Department purchased a Tractor and Boom Mower which improved the department's ability to cut the right of ways, clear ditches and remove low hanging branches. In doing so, Public Works is able to improve visibility for drivers and pedestrians on the road. It also keeps Valdosta beautiful - supporting the department's new motto "Love Where You Live".

 

Fire Department:

The Valdosta Fire Department unveiled four new fire trucks in November of 2016. The new trucks replaced four 18-year-old pumper trucks in its current fleet at stations 2,3,4 and 6. The new trucks are front-line pumpers that are custom-built with the latest and most updated equipment and meet the current National Fire Protection Association (NFPA) standards and the fire safety needs of the city.

Utilities:

  • EPD Sewer Collection System Requirements
  • Force Main Easements
  • Supplement Environmental Projects
  • Manhole/Liner Rehab
  • Sewer System Rehab
  • Sewer Collection Smoke Testing  - In July 2017, the City of Valdosta completed the smoke testing project for the sanitary sewer system, which included approximately 1,712,150 linear feet (over 300 miles).  The City hired Constantine Engineering to smoke test the entire sanitary sewer system and estimated that the project would take 4 years.  Work began in January 2014 and was completed ahead of schedule.  The purpose of this project was to identify and eliminate sources of stormwater inflow and infiltration (I&I) into the sewer system that cannot be identified by closed-circuit televising of sewer lines.
  • Withlacoochee Sewer Plant - Valdosta and Lowndes County voters who passed a continuation Special Purpose Local Option Sales Tax (SPLOST) referendum in 2013 were publicly credited for the debt-free opening of the City of Valdosta Withlacoochee Wastewater Treatment Plant (WWTP) at a ribbon-cutting event on July 12, 2016. Over 100 attended the event to tour the public facility that has been built to the highest standards and meets quality service delivery requirements for generations to come.

Other (inc. Parks and Rec, Mathis, Downtown):

 

On Wednesday, June 6, 2018, City of Valdosta leaders joined the Valdosta-Lowndes County Parks and Recreation Authority (VLPRA) to hold a ribbon cutting for the new playground at the Vallotton Youth Athletic Complex.

The $85,000 project was funded by City of Valdosta SPLOST funds. The new playground replaced the old, existing playground structure. The new playground will offer safer equipment to play on and will accommodate double the amount of children.

Public Information

229-259-3548

Public Information Officer

Ashlyn Becton

Location

Valdosta City Hall Annex
300 N. Lee Street, Suite #102
Valdosta, GA 31601

Public Information Events

Eastern Daylight Time